20 MW Wind Project, Zacatecas

The project is currently undertaking a new measurement cycle that is being certified to validate previous information with respect to the site of the project. A technical proposal for the interconnection was made and the measurement information was validated so as to confirm the project´s economic feasibility. The project currently holds title to the land, as well as a year of certified measurements.

The Environmental Impact Assessment has been contracted out and a layout of the wind generators was set to continue with the permitting process. The documents for the generation permit has been submitted to the Energy Regulatory Commission, and the contracting for the basic engineering of the switchyard and transmission line is underway. COD for the project has been established for the second semester of 2016.